Some pictures from the site visit on 30th October 2013, notable progress includes:
- Main wall completed at upper level
- Intermediate floor beams largely installed
- Work ongoing on upper bathroom - original wall restored.
- Fireplace restored
- Garden retaining wall almost complete
- Septic concrete walls completed
- Entry staircase work ongoing
- Roof completion to North end in progress.